Solar Energy Corporation Of India ... vs Wind Four Renergy Private Limited is a Supreme Court of India decision dated October 16, 2024 (citation: insc-2024-795). SECI challenged an APTEL order directing condonation of delay for a wind power project executed by Wind Four Renergy, a subsidiary of Inox Wind Infrastructure Services. The case involved a 50 MW wind power unit under a Power Purchase Agreement with delays in commissioning. The Supreme Court allowed the appeal in terms of its signed judgment. The bench comprised Justices Dipankar Datta and Sanjiv Khanna. The judgment was delivered by Justice Sanjiv Khanna.
Summary
SECI challenged an APTEL order directing condonation of delay for a wind power project executed by Wind Four Renergy, a subsidiary of Inox Wind Infrastructure Services. The case involved a 50 MW wind power unit under a Power Purchase Agreement with delays in commissioning. The Supreme Court allowed the appeal in terms of its signed judgment.
What was the outcome of Solar Energy Corporation Of India ... vs Wind Four Renergy Private Limited?
SECI challenged an APTEL order directing condonation of delay for a wind power project executed by Wind Four Renergy, a subsidiary of Inox Wind Infrastructure Services. The case involved a 50 MW wind ...
Judgment
Read the full judgment on the official India Courts portal.
Read on Indian KanoonSource: Indian Kanoon (insc-2024-795)