M/S Nelakuduru Infra Sriganesh Jv vs Northern Railway Anr Ors.

ik-66348614 Delhi High Court 20 December 2024 • 16 min read

Judges (1)

Counsel (7)

Parties (2)

Case Significance

M/S Nelakuduru Infra Sriganesh Jv vs Northern Railway Anr Ors. is a Delhi High Court decision dated December 20, 2024 (citation: ik-66348614). The petitioner, a railway construction contractor, filed an S.11 petition seeking constitution of an arbitral tribunal following termination of its contract with Northern Railway and a connected S.9 petition seeking interim protection against encashment of performance bank guarantees. The court appointed a sole arbitrator to adjudicate the disputes and directed the S.9 petition to be treated as an application under Section 17 before the arbitrator, while maintaining subsisting interim orders. The case was heard by Justice Sachin Datta.

Summary

The petitioner, a railway construction contractor, filed an S.11 petition seeking constitution of an arbitral tribunal following termination of its contract with Northern Railway and a connected S.9 petition seeking interim protection against encashment of performance bank guarantees. The court appointed a sole arbitrator to adjudicate the disputes and directed the S.9 petition to be treated as an application under Section 17 before the arbitrator, while maintaining subsisting interim orders. Both petitions were disposed of with interim protection continuing until the arbitrator's decision.

What was the outcome of M/S Nelakuduru Infra Sriganesh Jv vs Northern Railway Anr Ors.?

The petitioner, a railway construction contractor, filed an S.11 petition seeking constitution of an arbitral tribunal following termination of its contract with Northern Railway and a connected S.9 p...

Judgment

Read the full judgment on the official India Courts portal.

Read on Indian Kanoon

Source: Indian Kanoon (ik-66348614)