Bharat Heavy Electrical Limited & Anr vs M/S Koneru Constructions
Judges (1)
Counsel (11)
Case Significance
Bharat Heavy Electrical Limited & Anr vs M/S Koneru Constructions is a Delhi High Court decision dated November 26, 2025 (citation: ik-29967433). BHEL challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, specifically the award of escalation damages of Rs. 72,90,719 with 18% interest granted to the respondent contractor for civil works at a Power Grid substation in Tamil Nadu. The Court found the Arbitrator's method of computing damages — awarding 10% of the executed value on an ad-hoc basis — to be patently erroneous with no rational basis. The petition was allowed and the damages portion of the arbitr The case was heard by Justice Sachin Datta.
Summary
BHEL challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, specifically the award of escalation damages of Rs. 72,90,719 with 18% interest granted to the respondent contractor for civil works at a Power Grid substation in Tamil Nadu. The Court found the Arbitrator's method of computing damages — awarding 10% of the executed value on an ad-hoc basis — to be patently erroneous with no rational basis. The petition was allowed and the damages portion of the arbitral award was set aside.
What was the outcome of Bharat Heavy Electrical Limited & Anr vs M/S Koneru Constructions?
BHEL challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, specifically the award of escalation damages of Rs. 72,90,719 with 18% interest granted to the respondent co...
Judgment
Read the full judgment on the official India Courts portal.