Sri Ganesh Engineering Works vs Northern Railway & Anr. is a Delhi High Court decision dated December 10, 2024 (citation: ik-151193195). The petitioner sought appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act to adjudicate disputes arising from a Northern Railway construction tender for a Road Over Bridge near Ganaur Railway station on the Delhi-Ambala section. The court found that a valid arbitration agreement existed in the contract and that the disputes were arbitrable. A Sole Arbitrator was appointed under the aegis of DIAC, with respondents' rights to raise jurisdictional objections The case was heard by Justice Sachin Datta. Counsel appearing: Bachita Baruah Shukla (counsel for petitioner), Jagdish Chandra (counsel for respondent), Karan Khetani (counsel for respondent), Rahul Shukla (counsel for petitioner).

Summary

The petitioner sought appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act to adjudicate disputes arising from a Northern Railway construction tender for a Road Over Bridge near Ganaur Railway station on the Delhi-Ambala section. The court found that a valid arbitration agreement existed in the contract and that the disputes were arbitrable. A Sole Arbitrator was appointed under the aegis of DIAC, with respondents' rights to raise jurisdictional objections preserved.

What was the outcome of Sri Ganesh Engineering Works vs Northern Railway & Anr.?

The petitioner sought appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act to adjudicate disputes arising from a Northern Railway construction tender for a Road Ove...

Judgment

Read the full judgment on the official India Courts portal.