Nelakuduru Infra Sriganesh Jv vs Northern Railway & Ors. is a Delhi High Court decision dated December 20, 2024 (citation: ik-126758064). The petitioner joint venture sought appointment of a Sole Arbitrator under Section 11 of the Arbitration Act and interim relief under Section 9 to restrain invocation of performance bank guarantees following termination of a railway construction contract. The court appointed a Sole Arbitrator and directed that the Section 9 petition be treated as a Section 17 application before the Arbitral Tribunal, with existing interim orders continuing until disposal. The petitions were disposed of with a The case was heard by Justice Sachin Datta.

Summary

The petitioner joint venture sought appointment of a Sole Arbitrator under Section 11 of the Arbitration Act and interim relief under Section 9 to restrain invocation of performance bank guarantees following termination of a railway construction contract. The court appointed a Sole Arbitrator and directed that the Section 9 petition be treated as a Section 17 application before the Arbitral Tribunal, with existing interim orders continuing until disposal. The petitions were disposed of with all rights and contentions reserved.

What was the outcome of Nelakuduru Infra Sriganesh Jv vs Northern Railway & Ors.?

The petitioner joint venture sought appointment of a Sole Arbitrator under Section 11 of the Arbitration Act and interim relief under Section 9 to restrain invocation of performance bank guarantees fo...